1. Which of the following is NOT a process in the Project Integration Management knowledge area?

A. Develop Project Charter
B. Direct and Manage Project Work
C. Monitor and Control Project Work
D. Plan Project Procurement

Answer: D

2. Which of the following is NOT a tool or technique used in the Develop Project Management Plan process?

A. Expert Judgment
B. Project Management Information System (PMIS)
C. Project Management Methodology
D. Work Performance Data

Answer: D

3. Which of the following is NOT a process in the Project Scope Management knowledge area?

A. Collect Requirements
B. Define Scope
C. Verify Scope
D. Develop Schedule

Answer: D

4. Which of the following is NOT a tool or technique used in the Control Quality process?

A. Statistical Sampling
B. Inspection
C. Pareto Chart
D. Resource Optimization Techniques

Answer: D

5. Which of the following is NOT a process in the Project Risk Management knowledge area?

A. Plan Risk Management
B. Identify Risks
C. Control Risks
D. Develop Risk Response Plan

Answer: C

6. Which of the following is NOT a tool or technique used in the Plan Procurement Management process?

A. Make-or-Buy Analysis
B. Contract Types
C. Bidder Conferences
D. Resource Optimization Techniques

Answer: D

7. Which of the following is NOT a process in the Project Stakeholder Management knowledge area?

A. Identify Stakeholders
B. Plan Stakeholder Engagement
C. Control Stakeholder Engagement
D. Monitor Stakeholder Engagement

Answer: D

8. Which of the following is NOT a tool or technique used in the Estimate Costs process?

A. Analogous Estimating
B. Bottom-Up Estimating
C. Reserve Analysis
D. Resource Optimization Techniques

Answer: D

9. Which of the following is NOT a process in the Project Time Management knowledge area?

A. Define Activities
B. Develop Schedule
C. Control Schedule
D. Plan Resource Management

Answer: D

10. Which of the following is NOT a tool or technique used in the Monitor and Control Project Work process?

A. Expert Judgment
B. Project Management Information System (PMIS)
C. Change Control Tools
D. Resource Optimization Techniques

Answer: D